Connecting Manual Activity Connected Objects—Exercises
Required Data
Registering Manual Activity Connected Objects per Project
Purpose: The purpose of this exercise is to familiarize
you with the data that must be in place before you can perform the exercises below.
- Verify that the desired object types are allowed to be manually connected
to an activity for your project.
General exercise for
Creating Projects
Creating Activities
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- Create activities in your subproject structure.
- Save your changes.
General exercise for Building
Project Plan
Releasing Activities
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- Release some activities to which you want to manually connect objects.
General exercise for Executing
Activities
Creating Objects that can be Manually Connected to Activities
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- Create objects that you can later manually connect to activities. There
are a variety of different possible objects from which you can choose. For example,
you can create a document package, a purchase requisition or purchase order
line, or a shop order.
Main Exercise
Purpose: The purpose of these exercises is to show you how
to manually connect and disconnect objects to activities, either from the object
or from the activity. This lesson will describe this functionality in general.
Windows:
Project Navigator/Connections
Project Navigator/Activity
- Open the Project Navigator
window. (Alternatively, open the
Activity window.)
- Query for your project.
- In the Navigator, select the activity to which you want to connect your
object. (Alternatively, in the
Activity window,
select the desired activity in the Project list.)
- Click the Connections tab.
- Right-click and then click Connect/Disconnect Object. A window appears
which has a tab for each type of object which is allowed to be manually connected
to an activity in your project.
Note: The tabs that appear in the
Connect/Disconnect Object
window depend on which object types you allowed in the Registering Manual Activity
Connected Objects per Project Required Data exercise above. In addition, the tabs
that appear also depend on which executable you are using. For example, the
Shop Order tab will not appear
if the executable that you are running does not contain IFS/Shop Order.
- Click the tab for the object type that you wish to manually connect
to this activity (and that you created in the Required Data exercise above).
- Click Populate. All objects that are not currently connected to any
activity and that meet all necessary requirements, as well as those which are
manually connected to this activity are listed. Connect the desired object by
adding a check in the Connection checkbox. Click OK to save your
changes.
- Note that your object is shown in the upper table on the
Connections tab.
- Note that there is no check in the System Connection field as the
object was manually connected.
Note: You disconnect objects also in the
Connect/Disconnect Object
window.
- To disconnect a connected object from the activity, repeat steps
4-6 and click the tab for the object type that you wish to manually disconnect
from this activity.
- Disconnect the desired object by clearing the Connection checkbox.
Click OK to save your changes.
- Open the overview window or the detail window for the object type that you
wish to manually connect to an activity and populate this window with the object
that you created in the Required Data exercise above.
- Right-click, click Project Connection and then click Connect to
Activity.
- In the window that appears, select the desired activity to which your object
should be connected by selecting from the List of Values in the different fields
(program ID, project ID, subproject ID, activity ID, or activity sequence).
- Click OK to save your changes.
- Open the Project Navigator
window. (Alternatively, open the
Activity window.)
- Query for your project.
- In the Navigator, select the activity to which you have connected your object
in steps 3 and 4. (Alternatively, in the
Activity window,
select the desired activity in the Project list.)
- Click the Connections tab.
- Note that your object is shown in the upper table on the
Connections tab.
- Note that there is no check in the System Connection field as the
object was manually connected.
Note: Perform the following steps to disconnect the manually connected
object from the object.
- Repeat step 1, populating the window with the object that you
connected to an activity above.
- Right-click, click Project Connection and then click Disconnect
from Activity.
- Repeat steps 5 to 8.
- Note that the object is no longer shown in the upper table on the
Connections tab.
Copying forbidden: The material in this manual is protected by copyright law, and may not be copied entirely or in part, without the prior permission of Industrial & Financial Systems AB. © 2012 Industrial & Financial Systems AB