Entering Test Results for Manufacturing (Production Schedule)—Key Exercises
IMPORTANT |
It is extremely important that you set up and work within your own
site to maintain your data integrity. If you work within any other
site, you will compromise your own exercise data as well as the data of
other students. Predictable exercise results require that your data be
isolated in your own site. |
Basic Data Setup
Viewing a Control Plan for Manufacturing
Purpose: The purpose of this exercises is to view a
Manufacturing control plan used for entering test results for a production
schedule.
Menu Path: Quality Management/Control Plan/Control
Plan – Manufacturing
- Open the Control Plan – Manufacturing window.
- Query for the control plan for part no. 29-523, Rocker Arm.
- Verify that a control plan with Active status exists for the part.
General Exercise for Control Plan—Manufacturing
(Production Schedule)
Required Data
Purpose: The purpose of this exercise is to show how to enter a
production schedule line that will later be used to create an analysis.
Menu Path: Production Schedule/Production Schedule/Production
Schedule by Line
- Open the Production Schedule by Line window.
- Query for production line 29-M Milling at your site.
- Select a schedule line, right-click, and then click Generate Line
Schedule. The Generate Line Schedule window appears.
- Generate a schedule for part no. 29-523, Rocker Arm. Note: If
you do not know how to generate a schedule, go to General Exercise
for Production Schedules, or perform the following two steps.
- Select a schedule line and then create a new record. Enter a
schedule date. Also enter 29-523 in the Part No field and Rocker Arm in
the Part Description field. Finally, enter a value in the Qty
Scheduled field.
- Save the record.
Main Exercises
Purpose: The purpose of this exercise is to show how to create
an analysis from a production schedule line.
Menu Path: Production Schedule/Production Schedule/Production
Schedule by Line
- Open the Production Schedule by Line window.
- Select a production schedule line.
- Right-click and click Create Analysis. The Create Analysis
– Production Schedule window appears.
- The valid part revision and routing revision are shown by default. These fields can be updated
using the List of Values.
- Select the Routing
Operation No check box. An analysis will be created for the selected
operation.
- Create at least five analyses by selecting 5 in the No of Analysis
list.
- Select the Print Test Instruction check box.
- Click OK.
- The Report Print window appears. Click Preview.
- View the report and verify that the right test operations are listed.
- Close the report.
- Another window appears giving you the option to view an overview of
the analyses. Click Yes. The Overview – Production Schedules
Analysis window appears. The created analyses are listed.
Note: You can also create
analyses from the following windows:
- Production Schedule/Production Schedule/Production Schedule by Line Part (right-click
on a schedule line and then click Create Analysis)
- Production Schedule/Production Receipt/Production Receipt (right-click
in the header and then click Create Analysis)
- Production Schedule/Production Receipt/Report Point Receipt (right-click
in the header and then click Create Analysis)
Purpose: The purpose of this exercise is to show how to enter test results.
Menu Path: Quality Management/Control Plan/Control Plan
– Manufacturing
Quality Management/Analysis/Analysis Results
- You can begin this exercise in three ways:
Go to the Overview – Production Schedules Analysis window,
which you opened in the previous exercise, and select a line. Then right-click and
click Analysis Result. The Analysis Results – Production Schedule
window appears.
OR
Open the Control Plan – Manufacturing window and query for your current
control plan. Click the Production Schedule Analysis tab and select one
of the analyses you created in the previous exercise. Then
right-click
and click Analysis Result. The Analysis Results – Production Schedule
window appears.
OR
Open the Analysis Results window from the Navigator and query for
your analysis. The Analysis Results – Production Schedule
window appears.
- Verify that the status of the test operation lines is Incomplete.
- Select the Variable test operation line. The results will be shown in the
lower part of the window.
- Enter your test results and save the record. If you have entered results
outside the inner/outer min/max, you will receive a message
and the status of the test result line is set to Out of Specification. You can go ahead and save the
record if the test results are correct. If you have entered results inside the
inner/outer min/max, the status will be set to Within Specification.
- Right-click on the the test
operation line and then click Complete Registered Results.
- Verify that the status of the test operation line has
changed to Complete.
Purpose: The purpose of this exercise is to show how
to confirm
test results. When the test results are confirmed, they
can be included in
control chart and capability indices calculations.
Menu Path: Quality Management/Control Plan/Control Plan
– Manufacturing
Quality Management/Analysis/Analysis Results
- You can begin this exercise in three ways:
Go to the Overview – Production Schedules Analysis window,
which you opened in a previous exercise, and select a line. Then right-click and
click Analysis Result. The Analysis Results – Production Schedule
window appears.
OR
Open the Control Plan – Manufacturing window and query for your current
control plan. Click the Production Schedule Analysis tab and select one
of the analyses you created in a previous exercise. Then right-click
and click Analysis Result. The Analysis Results – Production Schedule
window appears.
OR
Open the Analysis Results window from the Navigator and query for
your analysis. The Analysis Results – Production Schedule
window appears.
- Right click in the header and then click Confirm Registered Result.
- Verify that the status has changed to Confirmed. Once the
analysis is confirmed, you can use the data for SPC follow-up.
Purpose: The purpose of this exercise is to show how to enter
test results for all analyses created from a production schedule.
Menu Path: Quality Management/Analysis/Analysis
Results
- Open the Analysis Results window.
- Enter the test results for all analyses.
- Open the Control Plan – Manufacturing window, click the
Production Schedule Analysis tab, and view the created analyses. These analyses will
later be used in
control chart and capability indices exercises.