Project Connected Work Orders—Exercises
Main Exercise
Purpose: The purpose of this exercise is to understand
how CBS can be used in conjunction with work orders that are connected to
projects.
IMPORTANT ! |
When performing the exercises below please replace all occurrences
of X with your site ID. This is to ensure that you work with your own data.
|
Create a Project
Purpose:
The purpose of this exercise is to
create a project plan that can be used to connect work orders.
Windows:
Projects
Create a project header
- Open the Projects window and create a new record.
- Enter values in the Project ID, Project Name and Project
Description fields according to the table below:
Project ID |
Project Name |
Project Description |
Planned Start |
Planned Finish |
Customer ID |
X-INSTALL |
Installation of RFID Equipment |
Installation of RFID Equipment |
Monday Next |
Friday two weeks from Planned Start |
Any customer |
- Save the information. Do not change the values or the company and manager.
- Select the project you just created, right-click and click Project
Details.
- In
Project/General
tab, enter the Planned Start and Planned Finish dates according to
the table above. Save.
- Click the
Site tab and create a
new record.
- Enter your site ID and save.
- Click the
Customer Info tab, enter a customer ID and save.
- Close the
window. You now have a project header.
Create sub projects and activities
Now we will create a number of sub projects and activities to
work with.
- In the Projects window, select the project you
created, right-click and click
Project Info.
- Click the Project
Navigator/Sub Project tab and create
a new record.
- Create the two sub projects outlined in the table below
and save:
Sub Project ID |
Sub Project Name |
Activity ID |
Activity Name |
Requested Start |
Total Workdays |
1 PREINST |
Pre Installation Activities |
10 |
Preparation |
Next Monday |
3 |
2 INSTALL |
Installation Activities |
20 |
Installation |
Next Monday |
3 |
|
|
30 |
Functional Test |
Next Monday |
3 |
- Click the
Activity List tab and enter the activities for
the relevant sub projects according to the table above.
- Save the information.
Add dependencies
Next we will add dependencies between the activities.
- Click tab Gantt tab.
- Select the main project node
(top node) from the project tree, the
Gantt tab will show all three
activities entered for the project.
- Right-click on the
Gantt tab and click Create Dependencies Mode.
- Draw a dependency line
between activity 10 and 20 then another between 20 and 30 and save.
- Right-click on the
Gantt tab and click Pointer Mode.
- Right-click again and click Schedule Project and save.
- Select the main project node (the top node), right-click, point to Status
and click Approve.
- In the dialog box that appears, select a Project Group using the List
of Values.
- Click OK. You now have a project to which you can connect work
orders.
Create Project Connected Work Orders
Purpose: The purpose of this exercise is to create a
number of work orders connected to the project.
Windows:
Prepare Work Order
Project Navigator
Create Work Orders
- Open the
Prepare Work Order window and create a new record.
-
Enter the first work order according to the table above below and save. Repeat
for the rest of the entries:
Work Order Site |
Directive |
Object Site |
Object ID |
Late Start |
Requested Finish |
Maintenance Organization |
X |
RFID Preparation |
X |
Any object on the site |
Tomorrow |
Tomorrow |
X-1000 |
X |
RFID Mechanical Installations |
X |
Any object on the site |
Tomorrow |
Tomorrow |
X-1000 |
X |
RFID Electrical Installations |
X |
Any object on the site |
Tomorrow |
Tomorrow |
X-2000 |
X |
RFID Functional Check |
X |
Any object on the site |
Tomorrow |
Tomorrow |
X-2000 |
Connect operations to each work order
- Click the
Operations tab and enter the operations for the relevant work
orders according to the tables below:
Work order directive = RFID Preparation
Operation No |
Description |
Maint. Org. |
Craft ID |
Planned Men |
Planned Hours |
10 |
Prepare for concrete |
X-1000 |
101 |
1 |
16 |
20 |
Pour concrete |
X-1000 |
101 |
2 |
8 |
- Create an operation dependency where operation 10 is the predecessor of
operation 20.
Work order directive = RFID Mechanical Installations
Operation No |
Description |
Maint.Org |
Craft ID |
Planned Men |
Planned Hours |
10 |
Drill hole |
X-1000 |
101 |
1 |
1 |
20 |
Mount pole |
X-1000 |
101 |
2 |
4 |
- Create an operation dependency where operation 10 is the predecessor of
operation 20.
Work order directive = RFID Electrical Installations
Operation No |
Description |
Maint. Org. |
Craft ID |
Planned Men |
Planned Hours |
Predecessor |
10 |
Install IP65 secured box |
X-2000 |
201 |
1 |
4 |
|
20 |
Connect 220V wiring |
X-2000 |
201 |
2 |
2 |
10 |
30 |
Install RFID reading device into
IP65 secured box |
X-2000 |
201 |
2 |
2 |
20 |
- Create operation dependencies according to the table above.
Work order directive = RFID Functional Check
Operation No |
Description |
Maint. Org. |
Craft ID |
Planned Men |
Planned Hours |
Predecessors |
10 |
Enable RFID tag |
X-2000 |
401 |
1 |
0,5 |
|
20 |
Drive by installation at 55 mph |
X-2000 |
401 |
1 |
0,5 |
10 |
30 |
Verify reading after 30 seconds on
the RFID web site |
X-2000 |
401 |
1 |
0,5 |
20 |
- Create operation dependencies according to the table above.
Connect the work orders to a project
- Click the
General tab, right-click, point to Project
Connection and click Connect To Activity.
- Using the List of
Values, enter the project, subproject and activity connections for the first
work order:
Directive |
Project ID |
Subproject ID |
Activity ID |
RFID Preparation |
X-INSTALL |
1 PREINST |
10 |
RFID Mechanical Installations |
X-INSTALL |
2 INSTALL |
20 |
RFID Electrical Installations |
X-INSTALL |
2 INSTALL |
20 |
RFID Functional Check |
X-INSTALL |
2 INSTALL |
30 |
- Click OK.
- Repeat steps 1-3 for the remaining three work
orders.
- Switch back to the
Project
Navigator window.
-
In the Connections tab, verify that the work orders are connected
for all activities.
You are now ready to schedule the project connected work orders!
Schedule Project Connected Work Orders
Purpose: The purpose of this exercise is to schedule a
set of project connected work orders.
Windows:
Active Work Orders
Work Order Simulation Client
- Open the
Active Work Orders window.
- Query
for work orders that are connected to your site and the project you created
above.
-
Select the records, right-click, point to Work Order Status and click Prepared.
-
In the dialog that appears, accept the default values and click
OK.
The entire project is now sent to the CBS Server for
scheduling. Check the value of the Scheduling Constraints field for
all project connected work orders. All work orders should be Resolved.
- Switch
over to the IFS Scheduling/Simulation Client (if you have closed
it open it through the Work Order Simulation Client).
- Query
for the
schedule from the CBS Server.
- In the Data Tree tab, there
is now a node that has your project ID. Expand the project node. The four work orders
that belong to the project should now be visible.
-
Clear the Gantt Chart.
- Click Settings on the menu
bar and click Plot Settings. In the Plot Settings
dialog box that appears select the Precedence Line
check box.
- Close the dialog box.
- Drag and drop your project onto the
Gantt
Chart.
- Drag the project item onto the
Drag & Drop Auto Timescale icon in the
Gantt Chart (
).
The dependencies between the work orders should now be visible. -
Right-click on the project node and click Show. The Need
Date field contains the Planned Finish date from the project.
-
Click the
Show Contents tab. The EPST (Earliest Possible Start Time)
field contains the
Planned Start date from the project.
- Close the dialog box.
Reschedule Project Connected Work Orders
Purpose: The purpose of this exercise is to understand
the available rescheduling options and how to perform rescheduling.
Windows:
Project Navigator
Work Order Simulation Client
- Switch back to the
Project
Navigator window.
- Right-click
the main project node (top node) and click Project Details.
-
Change the Planned
Start and Planned Finish dates to one month ahead.
- Save the
information.
-
Switch over to the Active Work Orders window.
-
Select a project connected work order, right-click and click Reschedule Work Order
Structure/Project.
- Accept default values and click OK. The project is now
rescheduled.
- Switch back to the IFS Scheduling/Simulation Client.
-
Query the schedule from the CBS Server.
- Right-click on the project node
and click Show. The Need Date should now have been moved
to one month ahead.
- Click the Show Contents tab. The EPST
date should now have been moved one month ahead as well.
- Close the
dialog box.
- Clear the Gantt Chart.
- Drag and drop your project onto
the Gantt Chart. Verify that the project has been rescheduled.
Enforcing Dependencies Between Work Orders
Purpose: The purpose of this exercise is to understand
how to work with the dependencies between work orders in a project environment.
Windows:
Active Work Orders
Work Order Simulation Client
- In the
Active Work Orders window, query for the RFID
Mechanical Installation (directive) work order.
- Right-click, point to Work Order Status and click Released. This work order should now be
released.
- For the same work order, change the status to Started. You should now get an error message saying that work orders
must be done in a dependency order.
- Perform step 3 for the RFID Preparation (directive) work order. This work order should now be
Started.
- Right-click and click Report In.
- Enter the Actual Start and
Actual Finish dates for this work order.
-
Right-click, point to Work Order Status and click Work Done.
- Switch
over to the IFS Scheduling/Simulation Client (Work Order
Simulation Client).
- Query for the schedule from the CBS Server.
-
Clear the Gantt Chart.
- Drag and drop your project onto the
Gantt Chart. The RFID Preparation work order should now
have been removed from the project structure. You should now also be able to
start the RFID
Mechanical Installation work order.
- Switch back to
Active Work Orders window and
set the status of the RFID
Mechanical Installation work order to Started.
- Report in this work order and set
the status to Work Done. Continue with
starting the next work order until you are done with the entire project.
Note: When the last work order has been reported in and the status set to Work Done, the
project should now be entirely removed from the CBS Server.