Connect Operation to Tools and Facilities

Explanation

This activity is used to define the operation that is planned to utilize the tools and facilities. This activity is a must if the operation is to be scheduled using IFS/CBS.

Prerequisites

System Effects

None

Window

Prepare Work Order
Work Order Execution Logic

Related Window Descriptions

Prepare Work Order
Prepare Work Order/Tools and Facilities

Work Order Execution Logic
Work Order Execution Logic/Tools and Facilities 

Procedure

Use the following procedure to connect operation to tools and facilities:

  1. Select the Tools and Facilities tab and use the New function.
  2. In the Tool/Facility Type field, use the List of Values to enter a tool or facility type. It is also possible to only enter a tool or facility ID. If that is the case use the List of Values in the Tool/Facility ID field and enter a tool or facility ID.
  3. In the Quantity field, specify the quantity of the tool or facility that will be used for the work order (if known).  
  4. In the Planned Hour field, specify the number of planned (if known).
  5. In the Operation No field, use the List of Values to select an operation line number. Save the information.