Unissue Part

Explanation

Use this activity to return to stock an inventory part that has not been used for a work order. You can unissue material as long as the work order is not reported or historical. 

Prerequisites

Before the information is entered,  the following must have been completed:

System Effects

As a result of this activity, the material costs on the work order is updated. This is displayed in the Budget tab, in the Actual Costs column. The Budget tab can be found in Prepare Work Order and Report In Work Order.

Window

Prepare Work Order, Report In Work Order,Report In Route

Related Window Descriptions

Prepare Work Order, Report In Work Order, Report In Route

Procedure

Use the following procedure to enter the information:

  1. Select the Materials tab.
  2. Select the Unissue operation.
  3. In the Quantity Unissue field, enter the quantity of the part to be returned to stock.
  4. Save the information.