Connect Requirement Activity

Explanation

When a part is connected to a requirement activity, the activity dates are used to determine need dates for material when running the right mouse button menu option Calculate Gross Requirement in Project Product/Demand/MPL tab.

Prerequisites

System Effects

Window

Project Product/Items
Project Item/Project Item

Related Window Descriptions

Project Product/Items
Project Item/Project Item

Procedure

  1. Select the part you want to connect to the activity.
  2. Use the List of Values to enter a requirement activity in the Activity Sequence field.
  3. Save.