Start Scheduling Client
Explanation
Use this activity to start the scheduling client. This enables you to reschedule the
operations using the drag-and-drop functions.
Prerequisites
This activity requires that a site connected to a Scheduling Server must exist.
System Effects
As a result of this activity the system reschedules the selected operations.
Window
Scheduling Client
Work Order Scheduling Client
Related Window Descriptions
Scheduling Client
Work Order Scheduling
Client
Gantt Chart
Data Tree
Procedure
- In the Site field, specify for which site you want to reschedule operations. Use
List
to select from the available sites.
- In the Time Limit field, specify how long you need to use the scheduling client.
- Specify whether the system should first
update the
material availability profile.
- Click OK. This updates the material availability profile, if specified,
and starts the scheduling client.