Manual Pegging of Shop Order Material Line

Explanation

Use this activity to connect existing supplies to demands. The system will retrieve available purchase order lines or shop order lines and present them in the corresponding tab. You can view what is available and decide which lines to connect. The connection is made to automatically allocate supplies to the pegged demands when supplies are received.

This activity can also be used to modify existing peggings. You can increase or decrease pegged quantities. A pegging may be removed. Reducing the pegged quantity to zero will remove the pegging. Validations are made so that the modifications cannot interfere with existing peggings. You can check existing peggings in the Purchased - Pegged Shop Order Material Lines and Manufactured - Pegged Shop Order Material Lines windows.

Prerequisites

System Effects

As a result of this activity pegging references are created. Pegged quantities are updated on the shop order. When the supply is received into inventory the quantity pegged is automatically reserved to the pegged demand.

Window

Manual Pegging of Shop Order Material Line

Related Window Descriptions

Manual Pegging of Shop Order Material Line
Shop Order
Manufactured - Pegged Shop Order Material Lines
Purchased - Pegged Shop Order Material Lines

Procedure

The Manual Pegging of Shop Order material Lines window could be opened from the Navigator directly. It is equally possible to open the same window from the windows Shop Order/Material tab, Manufactured - Pegged Shop Order Material Lines, or Purchased - Pegged Shop Order Material Lines by selecting the appropriate customer order line, right-clicking and then clicking Manual Pegging.

To create peggings of purchase order lines:

  1. Click the Purch Order tab to find available purchase order lines to create peggings for the shop order material line.
  2. Enter the quantity you want to peg in the Quantity Pegged field on the desired purchase order line. You can specify the amount to be pegged as long as the quantity is positive and is lower than the quantity available to be pegged.
  3. Save.
  4. If needed or desired you can create manual pegging against more than one supply (this can be both shop orders and/or purchase order lines).

To create peggings of shop order lines:

  1. Click the Shop Order tab to find shop order lines available to peg to the shop order material line.
  2. Enter the quantity you want to peg in the Quantity Pegged field of the desired shop order line. You can specify the amount to be pegged as long as the quantity is positive and is lower than the quantity available to be pegged.
  3. Save.
  4. If needed or desired you can create manual pegging against more than one supply (this can be both shop orders and/or purchase order lines).