Scrap with Edit Components
Explanation
Use this activity to declare scrap on the produced parts that occurred in the
manufacturing process. In order to backflush the correct components and operations, you
must specify the structure that was used when producing the part. This
list of components can then be updated using the edit components feature. You
cannot change the parent part, but you can specify an alternative structure. When
reporting an unscheduled scrap, the production schedule is not updated. 
Prerequisites
This activity requires the existence of a production schedule.
System Effects
	- As a result of this activity, the system reports scrap for the parent part and runs the
backflush process to consume the components. The user specifies whether the backflush
process is run directly or in the background If making a scheduled receipt, the
system automatically updates the production schedule. 
- If making an unscheduled receipt,
the system does not automatically update the production schedule. If inbound locations are
defined, they are used by the backflush in its search hierarchy.
- If an alternate component
substitution sequence is defined, it is used by the backflush when issuing material. 
	
- Inventory transactions are created for the scrap and all issued
components. 
- Operation history transactions are created for any backflushed machine or
labor operations. 
Window
Production
Receipt 
Production
Schedule by Line 
Production Schedule
by Line Part
Related Window Descriptions
Production Receipt 
Production Schedule by Line 
Production Schedule by Line Part 
Scrap Receipt 
Production Receipt Material 
Production Receipt Reservation
Procedure
From the 
Production Receipt window:
  - Open the 
	Production Receipt window.
- In the Production Line list, select the production line and part for which
    to report scrap.
- Right-click and then click Scrap Receipt. The 
	Scrap Receipt
    dialog box will appear.
- In the 
	Scrap Receipt dialog box, select 
	Immediate Backflush
    or Defer Backflush in the 
	Backflush list.
- In the Sched Option list, select 
	Unscheduled or 
	Schedule.
- In the  
	Structure area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the  Production Scrap area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click  
	List to select from
    available scrap reasons.  Optionally, if the catch
    unit is enabled 
	for the parent part, you can enter scrapped catch quantities.
    
- In the Report Point 
  area, select the 
	Complete Scrap check box to
    specify that this is the complete scrap for the manufacturing process.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material dialog box, type a value in the
    Qty To Issue field.
- To change components, click 
	New. The cursor appears in the
    Part To Issue field. Click 
	List to select from available parts. Next, type a
    value in the Qty To Issue field. 
- Save.
- To reserve the components before backflushing, select the components, then click 
	Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation dialog box, click 
	Create.
    The 
	Inventory Part Location dialog box will appear. 
- In the 
	Inventory Part Location dialog box, select a location.
    Click OK.
- In the 
	Production Receipt Reservation dialog box, type a value in
    the Qty Assigned field. Save 
  and then click 
	OK when the reservations
    are finished.
- When you have finished editing and reserving components, click 
	OK to run the
    backflush.
From the 
Production Schedule by Line window:
  - Open the 
	Production Schedule by Line 
	window. 
- In the Production Line list, select the production line for which to report
    scrap.
- In the table in the lower part of 
	Production Schedule by Line Part 
	window,
    select the production schedule for which to report scrap. 
	Right-click and then click Scrap Receipt. The 
	Scrap Receipt  
	dialog box will appear.
- In the 
	Scrap Receipt dialog box, select 
	Immediate Backflush
    or  Defer Backflush in the 
	Backflush list.
- Select  Unscheduled or 
	Schedule in the 
	Sched Option list.
- In the Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the Production Scrap 
  area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click 
	List to select from
    available scrap reasons.  Optionally, if the catch
    unit is enabled 
	for the parent part, you can enter scrapped catch quantities. 
    
- In the  
	Report Point area, select the 
	Complete Scrap check box to
    specify that this is the complete scrap for the manufacturing process.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material dialog box, type a value in the
    Qty To Issue field.
- To change components, click 
	New. The cursor appears in the
    Part To Issue field. Click 
	List to select from available parts. Next, type a
    value in the Qty To Issue field. 
- Save.
- To reserve components before backflushing, select the components, then click 
	Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation dialog box, click 
	Create.
    The 
	Inventory Part Location dialog box will appear. 
- In the 
	Inventory Part Location dialog box, select a location.
    Click OK.
- In the 
	Production Receipt Reservation dialog box, type a value in
    the Qty Assigned field. Save 
  and then click 
	OK when the reservations
    are finished.
- When you have finished editing and reserving components, click 
	OK to run the
    backflush.
From the 
Production Schedule by Line Part window:
  - Open the 
	Production Schedule by Line Part 
	window. 
- In the  Part No list, select the part for which to report scrap.
- In the table in the lower part of 
	Production Schedule by Line Part,
    select the production schedule for which to report scrap. 
	Right-click and then click Scrap Receipt.  The 
	Scrap Receipt 
	dialog box will appear.
- In the 
	Scrap Receipt dialog box, select  
	Immediate Backflush
    or Defer Backflush in the 
	Backflush list.
- In the Sched Option list, select 
	Unscheduled or 
	Schedule.
- In the Structure 
  area, specify the structure revision and
    structure alternate. If desired, also specify the routing revision and the routing
    alternate.
- In the Production Scrap 
  area, type the quantity scrapped in the 
	Qty
    Scrapped field. Click in the Scrap Reasons field, then click 
	List
    to select from available scrap reasons. Optionally,
    if the catch unit is enabled for the parent part, you can enter scrapped catch
    quantities. 
    
- In the  
	Report Point area, select the 
	Complete Scrap check box to
    specify that this is the complete scrap for the manufacturing process.
- To edit components, click 
	Components. The 
	Production Receipt
    Material dialog box will appear.
- In the 
	Production Receipt Material 
	dialog box, type the quantity
    to issue in the Qty To Issue field.
- To change components, click 
	New. The cursor appears in the
    Part To Issue field. Click  
	List 
	to select from available parts. Next, type a
    value in the Qty To Issue field. 
- Save.
- To reserve the components before backflushing, select the components, then click 
	Assign.
    The 
	Production Receipt Reservation dialog box will appear.
- In the 
	Production Receipt Reservation dialog box, click 
	Create.
    The 
	Inventory Part Location dialog box will appear. 
- In the 
	Inventory Part Location dialog box, select a location.
    Click OK.
- In the  
	Production Receipt Reservation dialog 
	box, type a value in
    the Qty Assigned field. Save 
  and then click 
	OK when the reservations
    are finished.
- When you have finished editing and reserving components, click 
	OK to run the
    backflush.