Update ESD According to Material Availability
Explanation
This activity is used to update the earliest start date
(ESD) according to the material availability.
Prerequisites
- The shop order (SO) should be in the Planned status.
System Effects
As a result of this activity:
- The earliest start date
of the SO will be updated according to the material availability. The Earliest Start Date field in the
Shop Order window will be updated
with the date in the Earliest Plannable Date column in the
Shop Order Availability window.
- If the SO is connected to a CBS site the earliest possible start time (EPST)
in the CBS server will be updated accordingly.
Window
Shop Order
Related Window Descriptions
Shop Order
Shop
Order/Detail
Procedure
- Open the
Shop Order window.
- Query for the required SO.
- Right-click on the header area and then click
Update ESD According to the Material Availability.
- Save the changes.