Create Complete Structure/Operations from BOM/Routing
Explanation
Use this activity to create a DOP structure by selecting a structure revision and
alternative and use the corresponding BOM structure.
Prerequisites
This activity has the following prerequisites:
- The DOP header status should be Created.
- The DOP structure
cannot be created for parts with a recipe structure.
- If the DOP
header part is serial effective and serial numbers are reserved, no selection of another
revision or alternative can be made.
- If no serial numbers are reserved, any valid revision
and alternative can be selected.
System Effects
As a result of this activity:
- A DOP structure is created from BOM. If
the DOP header is project specific, DOP Orders that are created in the structure
will be tagged with Project ID and Activity Sequence.
- If you have allowed an automatic release of DOP orders,
the system automatically releases the component DOP orders when the
structure is created. You specify this in the Auto Release field in the
DOP
Header/Detail tab. Releasing a DOP order means generating a shop order or a
purchase requisition for the DOP Order. The actual DOP order and the higher levels
structure will not be released.
- When releasing pegged project specific DOP Orders, the
system will generate project specific Shop Orders or Purchase
Requisitions/Purchase Orders dependent on the part type. These orders will be
received into project inventory.
- The status of the new DOP orders will change to Unreleased unless
the orders are automatically released. In that case, the status will be Released.
- When you create a DOP structure, any intermediate steps in the
structure are deleted. Parts with planning method K and P (blow through and phantom parts)
are considered intermediate steps. If a DOP order is serial effective, the breaking-down will
stop at the DOP order level and a log will be created. The log will be displayed in
DOP Logs. If you have allowed an automatic release of DOP orders, higher
levels structures straight to the top order will not be released. If serial numbers are
reserved for the DOP header, they are moved to the top DOP order.
- When creating a DOP structure which includes a phantom part, the DOP
order is created for the phantom part if there is enough inventory to
fulfill the order. Phantom parts are needed to net as and when the DOP order
is created to avoid material shortages in the future.
- A valid routing revision and buildable routing
alternative records will be added for each DOP order. If no buildable or plannable routing
alternative exist for the part a DOP log is created, but the creation of the structure
will continue. If the routing is serial effective and no serial numbers are reserved for
the DOP order a DOP log is created, but the creation of the structure will continue.
- The revised due date and the revised start date are calculated
for each DOP order in the structure, depending on revised due date and revised start date
of the parent DOP order, lead-time and lead-time offset, where the lead-time is
depending on lot size and routing revision and alternative. These lead-times will be calculated
based on the Manufacturing calendar, where as the Pegged Purchases will use the Distribution calendar.
Window
DOP Header
Related Window Descriptions
DOP Header
Procedure
- Open the DOP Header window.
- Right-click on the header area, point to Create DOP Structure and then click
Create DOP Structure, the
Create DOP Structure/Routings
dialog box will appear.
- Click
Create DOP Structure/Operations from BOM/Routing.
- Select the revision and alternative for the structure you want to use in the
BOM/Routing
area. Use the List of Value to select from available revisions and
alternatives.
- Click OK.