Select MRP Graph Parameters

Explanation

Use this activity to change the default values for the period range to be used for generating the Material Plan graph.

Prerequisites

This activity requires the existence of an Inventory (MRP) part (not a Level 0 or Level 1 part).

System Effects

As a result of this activity, the system uses the specified period range to generate the Material Plan graph.

Window

MRP Material Plan Graph

Related Window Descriptions

MRP Material Plan Graph
Recalculate Period Template
MRP Graph Parameters

Procedure

  1. In the MRP Material Plan Graph window, choose Show Graph from the RMB menu. The Select MRP Graph Parameters dialog box appears.
  2. Change the default values in the Begin No and End No fields by typing in new period numbers. (If you type a value of zero in the Begin No field, the system will consider all past due supply and demand when plotting the graph.)
  3. Click OK. The system generates a Material Plan graph for the specified period range.