[About Activities] [To Project Management]
Use this tab to view all activities with connected late purchase orders. A purchase order is late when the planned receipt date of the purchase order line is later than the required date of the miscellaneous demand. Alternatively for manually connected purchase orders, the part must be available in inventory not later than the early finish date of the activity.
Execute Activity
Analyze
Project Performance