Project Exceptions/Late Work Orders
Activity Exceptions/Late Work Orders
Usage
Use this tab window to view all activities with
late work orders. Only work orders with at least the status
Prepared should be included in the tab, and:
- If the activity's early finish date is earlier than
the work order completion date. However, if the work order has a value in
the WO Actual Completion field, this value should be used
instead of the completion date.
- Or if both WO Actual Completion and WO
Planned Completion are null.
Every
night an event message (ACTIVITY_WO_OUT_OF_SCOPE) is sent out, with all information regarding every issue for all projects.