Create Project Budget/Forecast Lines
Explanation
Budget/forecast lines contain the amounts retrieved from cost elements and
occasionally by code parts if code parts have been defined as mandatory in code
part demands for cost elements. A project
budget/forecast may consist of a number of lines for each cost element.
Prerequisites
- Cost elements for the project must be defined in the
Project
Details/Cost Element Code Part Demand
tab.
- The project budget/forecast version must exist with its status as Preliminary.
System Effects
- The budget/forecast line will be in the Under Review status.
Window
Project Forecast Version Lines
Project Forecast Info
Related Window Descriptions
Project Forecast
Version Lines
Project Forecast
Info/Costs
Procedure
Use the following procedure to add a budget/forecast line to an existing
budget/forecast
version:
- Open the Project Forecast Version Lines
window. You can also perform this activity by opening the
Project
Forecast Info window and clicking on the
Costs tab.
Note: When using the Costs tab of the
Project Forecast
Info window, you should query ahead for the project and the
budget/forecast
version for which you want to define a budget/forecast line.
- Click New to begin creating a new budget/forecast line.
- In the Project ID field use the List of Values to select the
project for which you want to define the budget/forecast line. Or if you want to
define the budget/forecast line down to the Sub Project Level or Activity Level use
the List of Values in the Sub Project ID field or Activity ID
field.
- In the Forecast Type field use the List of Values to select a
predefined budget/forecast type.
- In the Forecast Version ID field use the List of Values to select
a budget/forecast version defined on the project for which you want to create a new
budget/forecast line.
- In the Cost Element field use the List of Values to select a cost
element which you want to use for the budget/forecast.
- In the Description field enter a description for the
budget/forecast
line.
- In the Currency Code
field enter the currency code used for the budget/forecast values if
multicurrency budgeting and forecasting is
used (defined in the Project Details/Currency tab).
- Enter a value in either the ETC or EAC field
(If multicurrency budgeting and forecasting is used
enter the value in either transaction, project or base B&F rate currency). On saving if
one of these estimates/costs is the only one made on the budget/forecast line the
empty field will be left calculated to be equivalent to the field with the
value.
- In the Code Parts fields, use the List of Values where applicable
to select required values. Note: The Code Parts of a Cost Element for
which it is mandatory to define values are determined on the
Project
Basic/Cost Element Code Part Demands tab or
Project
Details/Cost Element Code Part Demand tab.
- Click Save.
Use the following procedure to confirm a budget/forecast line:
- Right click on a budget/forecast line and then click Confirm.
Use the following procedure to restart a review on a confirmed
budget/forecast line:
- Right click on a budget/forecast line and then click Start Review.