A description about the fields that summarize and display the costs/hours that are reported on objects connected to an activity is as follows.
Planned values represent the current budget which is valid for the activity. Planned values are retrieved from various connected objects, for example you can use tasks or document packages to define planned values, and these values will be summarized and displayed in the Planned columns. The value in the planned columns will be updated immediately when you change, add or remove objects that report planned cost/hours to the activity. You can also retrieve planned costs and hours from other sources by selecting a relevant Planned Cost Driver for the activity.
Baseline values represent the current approved budget which is valid for the activity. Use this column to keep track of the original approved plan, plus or minus approved scope changes. After a baseline has been created for a project the values entered in the Planned fields will be copied to the Baseline columns. If the planned values are changed thereafter, another baseline will have to be created for the new planned values to be reflected in the Baseline columns.
Planned Committed values are the sum of cost or hours from connected purchase requisitions lines, purchase order lines, shop order requisition lines and shop order lines which are not yet released.
Committed values are the sum of remaining costs or hours reserved or ordered by the objects connected to the activity. The total Committed value is reported first when the object reaches a status which commits its values (i.e. Released status on a Purchase Order) and decreases as Used values are reported from each connected object. For a connected purchase order, the committed value will be based on the remaining quantity to be received. For a connected shop order, the committed cost of material will be based on the quantity remaining to be issued, and the committed cost of work and hours will be based on the operation status and progress.
Used values are the sum of costs/hours that have been used, as reported from each connected object. Used Cost/Hours are reported from the transactions (Inventory, Purchase, Operation or Project) created by the object until these are transferred to IFS/Accounting Rules and the corresponding voucher is created. Once a transaction receives status transferred it will stop reporting used cost/hours and the voucher will instead report the Used Cost/Hours. Voucher rows that are created and pre-posted with Project ID and Activity sequence will always report Used cost/hours. The utilized hours will be displayed in the Actual Hours field.
Actual costs are the sum of costs that have actually been used as reported from General Ledger (through General Ledger Voucher Row). Actual hours are the hours that have been reported as used, from each object.
The calculated cost/hours and progress information can be viewed per activity in Project Navigator/Activity and Activity/General or per subproject or for the whole project in Project Navigator/Project.
The connected objects can report cost/hours and progress information to the activity. The type of information retrieved depends on the connected object. The possible information is Planned, Planned Committed, Committed, Used and Actual values defined against project cost elements. The Calculated Cost Progress and the Calculated Hours Progress fields show the cost and hours progress for the activity, respectively. It is calculated by dividing the earned value for cost/hours for each cost element by the sum of planned cost/hours and then shown as a percentage. The progress from the connected objects is updated to the activity according to cost or hours and cost elements.
The cost will be reported in the currency of the company associated with the project.
A description about the fields that summarize and display the revenue that is reported on objects connected to an activity is as follows.
Planned revenue represents either the budgeted values from an object (e.g. Invoicing Plan or Sales Contract Lines) or values generated through cost objects (e.g. Project Transactions) which have a sales price. The value in the Planned columns will be updated immediately when you change, add or remove objects that report planned revenue to the activity.
Preliminary revenue is always generated from a preliminary invoice.
Posted revenue is always generated from a Hold Table Voucher.
Actual revenue is always generated from a General Ledger Voucher and will also replace the value in the posted column.
The calculated revenue information can be viewed for each activity in the Project Navigator/Activity and Activity/General tabs. The Project Navigator/Project tab will show the revenue information for each subproject or for the entire project.
The revenue will be reported in the currency of the company that is associated with the project.
The costs, hours and progress on objects are updated for user defined project cost elements. Available progress methods are Duration, Manual, Template and All Connected Objects. More information regarding Progress Methods can be found in About Activity Progress Methods. Objects along with the cost and hours they report to the activity are given as follows.
Cost Object | Values | Cost | Hours |
Activity Task | Planned | Values are taken from the Planned Cost field in Tasks tab. | Values are taken from the corresponding Planned Hours fields in Tasks tab |
Activity Resources |
Planned
|
Values are taken from the Planned Cost field in the Resource/Resource Planning tab. The values are calculated based on the cost associated with the Resource ID and are updated when planned hours are entered. | Values are taken from the Planned Hours field in the Resource/Resource Planning tab |
Document Package | Planned | Values are taken from the Planned Cost field in the Document Package window. | Value is taken from the Planned Hours field in the Document Package window. |
Change Order |
Planned | Values are taken from the Planned Cost field in Change Order/Actions tab, CO Action Lines table. | Values are taken from the Planned Hours field in Change Order/Actions tab, CO Action Lines table. |
Design Object | Planned | Values are taken from the Planned Cost field on the Project tab of the Design Object window. | Values are taken from the Planned Hours field on the Project tab of the Design Object window. |
Project Misc. Demand | Planned |
Purchasing: For a Purchase Part/No Part/Inventory Part requirement line the cost is taken from the Planned Cost field in Planned Cost/Hours per Cost Element window (right mouse button menu option Cost Elements) and summed up to the Total Planned Cost field. Planned Cost is retrieved in the following order: 1) Expected Supplier Price per Unit, 2) Costing, 3) Inventory Value, 4) Estimated Cost. |
Purchasing: For a Purchase Part/Inventory Part/requirement line the cost is taken from the Planned Hours field in the Planned Cost/Hours per Cost Element window (right mouse button menu option Cost Elements) and summed up to the Hours Planned field. For a Purchase No Part requirement line the hours are taken from the Planned Hours field in the Planned Cost/Hours per Cost Element window (right mouse button menu option Cost Elements). |
Manufacturing: For supply option Shop Order, the values are taken from Costing depending on the setup in Posting Control. Non Std Planned items must be entered separately on the Miscellaneous Demand line. |
Manufacturing: Values are taken from the routing defined for the shop order (Shop Order/Operation tab). Non Std Planned items must be entered separately on the Miscellaneous Demand line. |
||
PMRP and DOP: For supply option PMRP and DOP, the values are taken from connected objects (PO, SO and MTR) depending on their setup. These supply options are using the full BOM (Bill of Material) for creating planned values. |
PMRP and DOP: Values are taken from connected objects (PO, SO and MTR) depending on their setup. |
||
Forecast Demand | Planned
|
Purchase Part: For a Purchase Part/Inventory Part requirement line the cost is calculated the same way it is done for Misc Demand/Misc Part. Planned Cost is retrieved in the following order: 1) Expected Supplier Price per Unit, 2) Costing, 3) Inventory Value, 4) Estimated Cost and is saved in the Project Navigator/Connections tab |
- |
Manufacturing Part: For a Manufactured Part the cost is calculated the same way it is done for Misc Demand/Shop Order. If the structure contains other forecasted parts, these will not be included in the planned value. They will have to be entered separately. The values are saved in the Project Navigator/Connections tab. |
- | ||
Project Misc Demand (Direct Issue from Inventory) | Planned | When a Purchase Part requirement line is entered. | |
Committed |
When several parts are required but only some are issued. The cost of the balance quantity will be taken as committed material. | ||
Used | When items are issued from standard inventory, or from project inventory (depending on the Material Allocation flag on the project). The cost is updated by the Inventory value. | ||
Work Order |
Planned
Planned for Purchase Requisition |
In the
Prepare
Work Order/ Operations tab enter a line for an employee, craft
or department, with planned hours that has a cost rate defined. In the Prepare Work Order/Materials tab create a line for a Part and specify the quantity required. This is for parts with the Supply Code Invent Order. In the Prepare Work Order/Planning tab create a line for the cost types either External or Expenses and specify quantity and cost required. In the
Prepare Work Order/Tools and Facilities tab create a line for
a Tool and specify quantity required. |
In the
Prepare
Work Order/ Operations tab enter a line for an employee, craft
or department, with planned hours. In Prepare Work Order/Tools and Facilities tab create a line for a Tool and specify quantity and hours required. |
Committed | Release the Work Order. | Release the Work Order. | |
Used | Report hours in the
Prepare Work Order/Tools and Facilities tab. Report time on the Report In Work Order/Time Report tab. Issue material with the Supply Code Invent Order in the Prepare Work Order/Materials tab. On the Report In Work Order/Postings tab enter posting lines for cost types either Expenses or External. |
||
Actual | Report time on the operations in
Report In Work Order/Time Report tab. Report hours in the Prepare Work Order/Tools and Facilities tab. |
||
Requirement Activity Info | Planned | Value is taken from Project Delivery/ Project Item/Cost Info tab. | Value is taken from Project Delivery/ Project Item/Hours Info tab. |
Used | Issue some standard planned items from Inventory by selecting the right mouse button menu option Issue from Inventory in Project Product/Items tab to update. | ||
Purchase Requisition line |
Planned Committed |
When a purchase requisition line is added for a Part/No Part and when it is released. | |
Purchase Order line | Planned Committed | When Purchase order is created for the Purchase Part/No Part and is in the planned state. | |
Committed | When a Purchase Order for a Purchase Part/No Part has been released. | ||
Used | When a Purchase Order for a Purchase Part/No Part has been received (upon ownership transfer). | ||
Purchase Order Change Order line | Planned Committed | The delta (in value) between the current purchase order and the active change order (includes statuses Planned, Released, Authorized) | |
Shop Order Requisition line | Planned Committed | When a shop order requisition line is added for a part through Project Material Requirements Planning (PMRP) or Project Master Scheduling (Project MS). | Values are taken from the routing defined for the part. |
Shop Order | Planned Committed | When the shop order is in Planned
state. Values are taken from the Planned Cost field in the Shop Order Costs/Project Cost Analysis tab. |
When a shop order is in Planned
state. Values are taken from the operations defined for the shop order. The number of planned committed hours for subcontracting operations is considered as zero. |
Committed | When the Shop Order is released. Values
are taken from the routing defined for the shop order (Shop
Order/Operation) When the Shop Order is released. Values are taken from the Shop Order components and Shop Order Costing (Shop Order Costs) When the Shop Order is released. Values are taken from the Shop Order routing and Shop Order Costing (Subcontracting) When the Shop Order is released. These values will be taken if General Overheads are defined in Part Cost tab. |
When the Shop Order is released. Values are taken from the routing defined for the shop order (Shop Order/Operation) | |
Used | Updated when reporting time and when issuing material to the Shop Order. | ||
Actual | Updated when reporting time on the Shop Order. | ||
DOP Header | Committed | Reported from connected DOP orders (SO, PO) through the DOP header. | Reported from the connected DOP orders (SO, PO). |
Used | Reported from connected DOP orders (SO, PO) through the DOP header. | ||
Actual | Reported from connected DOP orders (SO, PO) through the DOP header. | ||
Customer Order line | Planned | Depending on Supply option Planned cost is retrieved from the connected objects. Sales Overhead is retrieved from the CO line. | Depending on the Supply option Planned hours are retrieved from the connected objects. |
Committed | Updated by subsequent supply orders when they are released, and by the sales overhead from the customer order. | Updated by subsequent supply orders when they are released. | |
Used | Updated by subsequent supply orders when they are processed further, and by the sales overhead from the customer order. | ||
Actual | Updated by subsequent supply orders when they are processed further. | ||
Material Requisition Line | Committed | When the part is Reserved. For parts with Supply Code Invent Order. | |
Used | When the part is Issued. For parts with Supply Code Invent Order. | ||
Project Time Reporting | Committed | When time is reported on an activity. | When time is reported on an activity. |
Used | When the transactions are confirmed and the value in the Create Cost Accounting field is either Yes or No, Update Project Cost. | ||
Actual | When an employee reports time. | ||
Project Cost Reporting | Used | When cost is registered in the Project Cost Registration window. | |
Project Inventory Transfer | Used | When vouchers that are created for different transactions are stored in the Hold table they replace the Used value reported from the connected objects. | |
Voucher rows | Used | When vouchers that are created for different transactions are stored in the Hold table they replace the Used value reported from the connected objects. | |
General Ledger Voucher rows | Actual | When vouchers that are created for different transactions are updated to General Ledger the Actual Costs are updated. | |
Sub Contract | Planned | The Planned Cost is reported automatically when the revision is activating . Planned Cost is reported before activating the revision when selecting the Report Planned Cost check box. Planned Cost is updated when selecting Update Planned Cost menu option. | |
Planned Committed | When awarding the sub contract, Planned Committed Cost is reported. | ||
Committed | When releasing the Call Off, Committed Cost is reported. | ||
Used | When receiving application after creating the valuation. |
Updating of revenue on objects is performed against user defined project revenue elements. Revenue objects does not report progress. The objects along with the revenue they report to the activity are given as follows:
Revenue Object | Values | Revenue |
Invoicing Plan | Planned | When the Invoicing Plan Line is created with the Sales Amount. |
Sales Contract and Application for Payment |
Planned
|
Retrieved from Sales Contract Line Items that have the Active revision status. The Report Planned Revenue checkbox can be used to view the previously planned revenue. |
Posted | Used if there is a Posting Control setup for AFP vouchers including Project ID and Activity Seq. | |
Actual | Used if there is a Posting Control setup for AFP vouchers including Project ID and Activity Seq. | |
Work Order | Planned | When the Work Order Line is transferred to a Customer Order Line. |
Customer Order |
Planned | When a Customer Order Line is connected to an activity. |
Customer Order Invoice | Preliminary | When a Customer Order Invoice is created. |
Posted | When the Customer Order Invoice is posted. The values will be fetched from the Hold table voucher. | |
Actual | When the Customer Order Invoice hold table voucher is updated to the General Ledger. | |
Project Invoice | Planned |
When a Project Transaction is entered which can be invoiced and has a Sales Price. |
Preliminary | When the Project Invoice is saved in preliminary state. | |
Posted | When the Project Invoice is posted. The values will be fetched from the Hold table voucher. | |
Actual | When the Project Invoice hold table voucher is updated to the General Ledger. | |
Instant Invoice | Preliminary | When the Instant Invoice is saved. |
Posted | When the Instant Invoice is posted. The values will be retrieved from the Hold table voucher. | |
Actual | When the Instant Invoice hold table voucher is updated to the General Ledger. | |
Customer Invoice | Preliminary | When the Customer Invoice is saved. |
Posted | When the Customer Invoice is posted. The values will be fetched from the Hold table voucher. | |
Actual | When the Customer Invoice hold table voucher is updated to the General Ledger. | |
External Customer Invoice | Preliminary | When the External Customer Invoice is populated. |
Posted | When the External Customer Invoice is posted. The values will be fetched from the Hold table voucher. | |
Actual | When the External Customer Invoice hold table voucher is updated to General Ledger. | |
Manual Voucher | Posted | When the Voucher is saved in the Hold table. |
Actual | When the voucher is updated to the General Ledger. | |
General Ledger | Posted | When vouchers that are created for different transactions are stored in the Hold table they replace the Posted value reported from the connected objects. |
Actual | When vouchers that are created for different transactions are updated to General Ledger the Actual Revenue is updated. |
Note:
Project Navigator
Project Navigator/Activity
Project Navigator/Activity List
Project Navigator/Connections
Project Navigator/Project
Activity/General
Activity/Connections
Project
Navigator
Project
Navigator/Activity
Project
Navigator/Activity
List
Project
Navigator/Connections
Project
Navigator/Project
Activity/General
Activity/Connections
For this example we work on a project containing only one activity called: "Specify and purchase engine for winch". In order to complete this activity some engineers have to do a detailed specification of which engine to buy, and later the purchase department is involved in the communication with the selected supplier.
Step 1
Project Cost Element Estimated Cost Estimated Hours Material 100,000 Work 3,000 30
Sum 103,000 30
Step 2
Now we get the following results:
Project Cost Element Estimated Cost Planned
CostEstimated Hours Planned Hours Material 100,000 Work 3,000 3,200
30
32 Sum 103,000 3,200
30
32
Step 3
Now we get the following results:
Project Cost Element Estimated Cost Planned
CostEarned Value - Cost Scheduled Work - Cost Estimated Hours Planned Hours Earned Value - Hours Scheduled Work - Hours Material 100,000 Work 3,000 3,200
1,600
800
30
32
16
8
Sum 103,000 3,200
1,600
800
30
32 16 8
Step 4
Now we get the following results:
Project Cost Element Estimated Cost Planned Cost Earned Value -
CostScheduled Work -
CostCommitted Cost Estimated Hours Planned Hours Earned Value - Hours Scheduled Work - Hours Material 100,000 90,000 22,500 90,000 Work 3,000 3,200 3,200 800 30 32 32 8 Sum 103,000 93,200 3,200 23,300 90,000 30 32 32 8
Step 5
Now we get the following results:
Project Cost Element Estimated Cost Planned Cost Earned Value -
CostScheduled Work -
CostCommitted Cost Used Cost Actual Cost Material 100,000 90,000 45,000 90,000 Work 3,000 3,200 3,200 1,600 900 Sum 103,000 93,200 3,200 46,600 90,000 900
Project Cost Element Estimated Hours Planned Hours Earned Value - Hours Scheduled Work -
HoursActual Hours Material Work 30 32 32 16
10 Sum 30 32 32 16
10
Step 6
Now we get the following results:
Project Cost Element Estimated Cost Planned Cost Earned
Value -
CostScheduled Work -
CostCommitted Cost Used Cost Actual Cost Material 100,000 90,000 45,000 90,000 45,000 45,000 22,500 Work 3,000 3,200 3,200 3,200 2,250 2,250 Sum 103,000 93,200 48,200 93,200 45,000 47,250 24,750
Project Cost Element Estimated Hours Planned Hours Earned Value - Hours Scheduled Work -
HoursCommitted Hours Actual Hours Material Work 30 32 32 32
25 Sum 30 32 32 32
25