Schedule Project Plan
Explanation
The project schedule is established when the planned
early start and early finish dates have been determined for all project
activities. The activity start and finish dates are either entered manually
or determined through a scheduling calculation.
To manually establish the project schedule, values for activity dates and work
days are directly entered for each activity. It is also possible to update
activity early start and early finish dates by dragging or moving activity bars
in the Gantt chart.
Alternatively, a scheduling calculation can be performed to determine the
activity start and finish dates. Logical dependencies are created between
activities to form an activity network, which is used as input into a scheduling
calculation. Scheduling will result in updated activity start and finish dates,
and critical activities will be indicated. The scheduling calculation takes the
following into account:
- The project calendar (working and non-working
days)
- The project start date or if none, the earliest
activity start date
- Information about activity dependencies
(predecessor, successor, dependency type and lag)
- The number of work days for each activity
- Constraints
- Actual start and finish dates
The scheduling calculation in IFS/Project only
works with days as the planning unit, for example 1 day, 2 days, etc. The
selected timescale in the Gantt does not affect the scheduling calculation but
is used for display purposes only.
Prerequisites
- Activities must exist.
- You must have access to the entire project to schedule a project.
System Effects
- When activity early start and finish dates are
updated, either manually or through scheduling, the Gantt chart is updated.
- If activity bars in the Gantt chart are dragged or
moved, the corresponding activity early start and finish dates are updated.
- If a scheduling calculation is performed, the
following values are updated:
- The activity early start and early finish
dates
- The activity late start and late finish dates
- The free and total float for each activity
- The project start and finish dates
- Changing activity early start and finish dates,
either manually or through scheduling, can affect objects that may be
connected to the activity:
- The Required Date for a miscellaneous demand or a
connected project delivery item is based on the activity early finish date.
- Project exceptions may be created.
- The period to which resources are assigned follows
the activity early start and early finish dates.
- Employee allocations with specific Date From and
Date To and that are not fixed, follow the activity early start and finish
dates. Fixed allocations will not be moved.
- Employee allocations without specific Date From
and Date To follow the activity early start and early finish dates as
allocation dates.
Window
Gantt
Project Navigator/Planning
Activity/Planning
Related Window Descriptions
Project Navigator/Gantt
Project Navigator/Planning
Activity/Planning
Procedure
To manually update activity early start and finish dates:
- In any window with activity information, change the
value of the early start date or the early finish date, alternatively the
number of work days.
- To manually update activities in the
Gantt tab,
drag on the ends of the activity bars or drag the entire bar to another
date.
To create an activity network:
- In the Gantt tab, right-click and click Properties to open the
Gantt Properties
dialog. Check that the Show Dependencies check box is selected.
- Right-click and click Create
Dependencies Mode so that you can draw dependencies between activities
directly in the Gantt chart.
- Drag the pointer from one (predecessor) activity
to another (successor) activity to create a finish-start dependency. Save
your changes.
- Pointing to a dependency, right-click and click Dependency Details. In the
Dependency Details
dialog, it is possible to change the dependency type, add a value for lag,
or delete the dependency.
- Dependencies information can also be added,
updated or deleted in the Planning/Predecessors or
Planning/Successors tabs.
- Information about constraints is added in the
Planning/Constraints tab.
To schedule a project:
- In the
Project
Navigator window, query for
the project that you wish to schedule.
- Select the project level in the project navigator
and select the
Gantt tab.
- In the Gantt tab, right-click and click Schedule Project. Alternatively, you can select the
Refresh Client & Schedule Project function to first refresh the
Gantt client with the latest activity
information before performing the scheduling calculation. This second alternative should be used if activity
information has been changed in another window after the
Gantt window has been populated.
- The results of the scheduling calculation can be
previewed in the
Gantt tab.
- Save the changes to commit the results of the
scheduling calculation.