Register Received Returns
Explanation
When receiving the material which is returned from customers, you should enter all the
returned parts. In this way you can verify if there are any discrepancies between what was
actually received and what the customer was authorized to return. The parts must have been
entered as received before you can enter the handling of the returned material. The
alternatives for handling returns of inventory registered parts is either to scrap the
returned material or to return the material to the inventory.
If the internal customer and the site at which the parts are returned belong to the same company, there is a different procedure.
For these internal customers, parts are directly registered as either scrapped
or returned.
You also can enter returns of non-inventory parts. When all parts on a return material
authorization line with non-inventory parts have been received, the line will
automatically acquire the Return Completed status. This means that non-inventory parts do
not need to be handled.
Prerequisites
- The current RMA line must have been released.
System Effects
- If only a part of the quantity approved for return is received, the RMA line will
acquire Partially Received status.
- When all parts on a RMA line with inventory parts have been received, the line will
automatically acquire Received status.
- When all parts on a RMA line with non-inventory parts have been received, the line will
automatically acquire Return Completed status.
- When all material on an entire RMA has been entered as received, the RMA header status
is updated to Received status.
- When an inventory part has been entered as received, it is possible to enter the part
as scrapped or returned into inventory.
- When a non-inventory part is entered as received, postings are created immediately.
After this you can no longer update prices and customer order line information on the RMA
line.
Window
Return Material
Authorization
Return Material Authorization Lines
Receive
Authorized Returns
Related Window Descriptions
Return Material Authorization
Return Material Authorization Lines
Receive Authorized Returns
Return Material - Receive, Scrap and Return
into
Inventory
Return Parts from
Internal Order Transit
Scrap
Parts from Internal Order Transit
Procedure
A complete RMA line has been returned:
- Populate, or query for the appropriate RMA.
- Mark the appropriate RMA line or lines. Right click in the lower part of the window and
select Receive Complete Lines in the operations menu.
- Close the window
Parts of a RMA line has been returned:
- Populate, or query for the appropriate RMA.
- Mark the appropriate RMA line. Right click in the lower part of the window and select
Receive, Scrap and Return into Inventory... in the operations menu.
- In the Quantities - Sales/Invent Units group box, you can choose to enter the received
quantity in either sales unit of measure or inventory unit of measure. To use the
sales unit of measure, enter the quantity in the Received Qty field in the upper row. To
use the inventory unit of measure, enter the quantity in the Received Qty field in the
lower row.
- To save the changes without closing the window, click the Apply button. The value in the
Total Qty Received field will then show the total quantity of the current part that has
been entered as received. The value in the Left to Handle field will show the quantity of
the current part that has not yet been entered as scrapped or returned to the inventory.
- To save the changes and close the window, click the OK button.
Parts are returned from an internal customer that
belongs to the same company as the site at which the parts are returned
belongs:
- Populate or query for the appropriate RMA.
- Mark the appropriate RMA line. Right-click in the lower part of the window and
then click Return Parts from Internal Order Transit or Scrap Parts from Internal
Order Transit depending if the parts should be scrapped or returned.
- Enter the quantity to be returned or scrapped in the
lower section of the dialog box.
- To save the changes and close the dialog box, click OK.
Note: For more details regarding scrapping and returning