Spreading Costs—Exercises
Required Data
Enter Version Lines
Purpose: The purpose of this exercise is to show you the
required data that is used in the exercises below.
- Enter 3 budget/forecast lines on a project budget/forecast.
General exercise for
Enter Forecast
Lines
Main Exercise
Purpose: The purpose of these exercises is to spread the
costs in a project in three different ways and confirm the version lines.
Windows:
Project Forecast Info
Spreading Cost Manually
- Open the Project
Forecast Info window and query for the project budget/forecast for
which you created budget/forecast lines.
- Make sure that the Spread Type field in the first budget/forecast
line on the Cost
tab has the value Manual selected.
- Select the first budget/forecast line, right-click and click Forecast
Spread Details.
- Select 4 in the Number of Periods field and observe that four
columns with months appear in the table.
- Enter values in the four months so that the total would be the value in
the Un-spread Amount field.
- Save the record (F12).
Spreading Cost using Straight
Line Method
- Open the Project
Forecast Info window and query for the project budget/forecast for
which you created budget/forecast lines.
- On the Cost
tab, select the value Straight Line in the Spread Type field for
the second version line.
- Save the record (F12).
- Select the second budget/forecast line, right-click and click Spread
Forecast Amount.
- Make sure Use Spread Type from Line is selected and click OK.
- Select the second budget/forecast line, right-click and click Forecast
Spread Details and observe how the amount has been spread through the months.
Spreading Cost using S-Curve
- Open the Project
Forecast Info window and query for the project budget/forecast for
which you created version lines.
- On the Cost
tab, select the value S-Curve in the Spread Type field for the
third budget/forecast line.
- Enter 4 in the Gradient field and 0.4 in the Mid
Point field for the third budget/forecast line.
- Save the record (F12).
- Select the third budget/forecast line, right-click and click Spread Forecast
Amount.
- Make sure Use Spread Type from Line is selected and click OK.
- Select the third budget/forecast line, right-click and click Forecast
Spread Details and observe how the amount has been spread through the months.
Confirming Budget/Forecast Lines
- Open the Project Forecast Info window
and query for the project budget/forecast.
- Select the rows in the
Cost tab and click Confirm.