Assigning and Analyzing Resource CapacityExercises
Required Data
Registering Resource Groups
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- Register a resource group.
- Save your changes.
General exercise for Registering
Resource Groups
Creating Activities
Purpose: The purpose of this exercise is to familiarize you with the data
that must be in place before you can perform the exercises below.
- Create activities in your subproject structure.
- Give activities appropriate early start and early finish dates.
General exercise for Building
Project Plan
Main Exercise
Purpose: The purpose of these exercises is to show you how
to assign resources to activities. You will also calculate and evaluate the usage
of resources for one or more projects, and compare it to the resource group's capacity.
On the basis of your resource capacity analysis, you will identify problem periods.
You will try various actions to solve resource allocation problems.
Windows:
Project Navigator/Resource
Project Navigator/Activity
Project Navigator/Project
Resource Group/Activities
Resource Capacity Calculation
Resource Capacity Calculation/Projects
Resource Capacity Calculation/Resource Summary
Resource Capacity Calculation/Resource Detail
- Open the Project Navigator
window and query for your project.
- Select the desired activity in the Navigator, and then click the
Resource tab.
- Create a new record. The resource company is set automatically to the project
company.
- Enter one of your registered resource groups, or select one from the List
of Values.
- There are two possible values for the duration type: Fixed and Resource.
This value can be changed.
Note: The Duration Type field is only in use when interfacing with
Primavera. Fixed value means that the activity's start and finish dates are preserved.
When using the resource option, Primavera will adjust the activity finish date according
to how fast the resource can execute the activity. This finish date can be set to
either an earlier or a later date.
- In the Planned Hours field, specify the planned number of hours that
the resource group should work on this activity.
- Save your changes.
Note: If the resource does not have cost or capacity defined
for the period of the activity, you will get a warning. You should then specify
cost and/or capacity for the activity duration period. To be able to do this quickly,
click the Resource ID field, and then click the Zoom button
on the toolbar. This opens the
Resource Group window,
and you can specify cost and capacity in the corresponding tab.
- Note that the Planned Cost field is automatically updated according
to the cost information from the Resource Group/Cost
tab, or the Resource Group/Standard Price
tab if you have selected a project reporting resource. Observe also that the
value in the Cost Element field is updated from the cost element defined
for this resource on the
Resource Group window.
- Repeat steps 38 to add additional resources to this activity.
- Click the Activity
tab.
- In the Planned Cost Driver list, click Connected Objects.
Save your changes.
- Click the Cost and
Hours tabs. Observe the values in the
Planned column.
- In the Planned Cost Driver list, click Activity Resources.
Save your changes.
- On the Cost and
Hours tabs, note that the values in the
Planned column now correspond with the planned values for the connected
resources. Note also that the these planned values update the correct project
cost elements.
- Click the Resource
tab again.
- Revise the value in the Planned Hours field.
- Save your changes.
- Note that the value in the Planned Cost field is updated according
to your revision.
- Go back to the Activity
tab.
- Note that the values in the Planned columns on the
Cost and Hours
tab are also updated according to your revision in the
Resource tab.
- Open the Project
window.
- In the Resources Summary
tab, the planned hours and cost for each resource are presented
- In this table, the planned hours and cost for each resource and subproject
are presented and summarized for the whole project.
- Open the Resource Group
window, and query for your resource. (You can also zoom directly to your resource
as described in the above note.)
- Click the
Activities tab, where you can see all the activities in all projects
to which this resource has been allocated. Use the query function to query only
for activities in your project.
Note: For an example of activities with allocated resources, you can refer
to Project P101 and Activities 10020 and 10030. Resource Groups E10 and E20 have
been allocated to these activities. Note that the planned cost for Resource E10
allocated to Activity 10020 considers the change in internal price that occurs during
the period of the activity. The 180 planned hours are assumed to be spread evenly
among the activity's workdays, which means that half the planned hours are planned
to occur in the first cost period in this example. The planned cost is calculated
as follows: (180 * 5/10 * 80) + (180 * 5/10 * 90) = 15,300 USD.
Resource ID |
Activity |
Early Start |
Early Finish |
Work Days |
Planned Hours |
Planned Cost |
E10
Cost = 80 USD per hour from 20010101 to 20010930
Cost = 90 USD per hour from 20011001 to 20021231
Normal capacity = 20 hours per day
Max capacity = 24 hours per day
|
10020 |
20010924 |
20011005 |
10 |
180 |
15,300 |
10030 |
20011001 |
20011012 |
10 |
80 |
7,200 |
E20 project reporting resource
Internal price = 100 USD per hour from 20010101 to 20021231
Normal capacity = 6 hours per day from 20010101 to 20011005
Normal capacity = 8 hours per day from 20011006 to 20041231
Max capacity = 10 hours per day
|
10030 |
20011001 |
20011012 |
10 |
10 |
1,000 |
- Open the Project Navigator
window, and query for your project.
- Select one of the activities that you worked with in the above exercise
in the Navigator. Click the
Resource tab.
- Select the desired resource, right-click, and then click Resource Allocation
to open the Resource
Allocation Graph. (Alternatively, access this graph from the
Resource Group/Activities window. For the
desired resource, select the desired activity. Right-click and then click
Resource Allocation.)
- You can now see the selected activity's allocation of this resource represented
in one color, and the allocation of this resource for all other activities in
a different color. The normal capacity is shown by a horizontal line. This gives
you an overview of this resource's allocation during the activity's length.
Note: The Resource
Allocation Graph considers all activities to which this resource has
been assigned, regardless of the project status. Compare with the resource capacity
calculation, where you can manually select which projects to include when calculating
the resource allocation. This can be useful, for example, if you want to disregard
projects that are not yet approved, canceled projects, etc.
Note: Referring to the above example, you should see that Resource Group
E10 is allocated for more than its normal capacity during the last five days of
the activity as planned, indicating that you might want to do a more detailed analysis
of the resource allocation. You might want to do a resource capacity calculation,
as described in the next exercise.
- Open the Resource
Capacity Calculation window, and create a new record.
- Enter a new calculation ID. Name it XX01, substituting XX with your initials.
- Note that the calculation can be based either on the early start/finish
activity dates or the late start/finish dates. Click Early Start/Finish.
- Specify whether the resource capacity should be calculated for a weekly
or monthly period.
- Save your changes.
- Click the
Projects
tab.
- For each project that you would like to include in the calculation, create
a new record, and enter the desired project ID.
Note: If you only want to consider projects in a specific status, or belonging
to a specific company or project program, perform a query in the
Projects window to identify
suitable projects. Alternatively, in the
Activity Resources
window, query for all the activities to which your resource is allocated, and thereby
identify their projects.
- Save your changes.
- Right-click anywhere in the header portion of the
Resource Capacity Calculation
window, and click Process Projects. A message appears indicating that
if you previously calculated resource capacity using this calculation ID, the
data will be lost.
- Click Yes.
- You can choose to run this calculation immediately or as a background job.
Do not select the Run the Procedure in Batch Mode check box so that your
calculation is performed immediately. Click OK.
- You can see the results of the calculation on the
Resource Summary and
Resource Detail tab.
- Click the
Resource Summary tab. Note the values for your calculation.
- You can view the calculation results graphically in the
Resource Capacity Summary
Graph. Right-click anywhere in the header portion of the
Resource Capacity Calculation
window, and click Resource Graph.
- In the Resource ID list, note that all resources that have been allocated
in the selected projects are available.
- Alternatively, select a row in the
Resource Summary tab or
Resource Detail tab, right-click, and then click Resource Graph.
The Resource Capacity
Summary Graph appears. Only the selected resource will be in the
Resource ID list.
Note: For an example of a resource capacity calculation, you can refer
to the capacity calculation ID P101, which considers Project P101 and the allocated
resources as described above.
Look at the resource capacity summary for Resource ID E20. You will see that
the resource has a normal capacity of 30 hours for a number of weeks, but then the
normal capacity changes to 40 hours. This change is due to a specified change in
capacity for this resource, as defined on the Resource
Group/Capacity tab. The capacity for the first period is 6 hours/day,
and then it becomes 8 hours/day. To obtain the period's capacity, multiply the defined
capacity per day by the number of workdays according to the calendar for this resource
(e.g., 6 * 5 = 30 and 8 * 5 = 40).
Looking at the resource capacity summary for the resource ID E20 again, note
that Week 47 has a normal capacity of only 24 hours. The decrease in available capacity
is a reflection of the resource calendar US5, which includes American holidays.
In this calendar, Week 47 has only 3 working days. The normal capacity for this
week will then be 3 * 8 = 24. To see calendar details, open the
Calendar window.
- Open the Resource
Capacity Calculation window, and query for your calculation.
- Right-click anywhere in the header, and then click Resource Graph
to open the Resource
Capacity Summary Graph. You will now see the results of the calculation
shown weekly or monthly according to your selection. The results are presented
in both a table and a graph. The values for each period are shown as one row
in the table, or as one bar in the graph.
- If desired, select some periods in the table, right-click and then click
View Graph to reduce the number of periods displayed at a time in the
graph.
- You can choose to show a legend that explains the different colors in the
graph. Right-click anywhere in the graph, and then click Enable/Disable Legend.
- You can easily identify the periods where the resource is overloaded, indicated
by the red-topped bars. Alternatively, you can use the query function in the
table and query for periods having overload > 0.
- When you click a bar in the graph, the
Resource Period Detail
window opens, displaying detailed information about the resource
allocation for this period. Alternatively, select one period in the period table
to the left of the graph, and then right-click and select Resource Period
Detail.
Note: The
Resource Period Detail
window lists the activities to which you have allocated the resource, but only
if you have access to the activity. If you do not have access to an activity, however,
the number of hours allocated still will be included in the Load Hours field
in the Resource Capacity
Calculation window and the
Resource Capacity Summary Graph.
- Try different methods of eliminating periods of resource overload. For example,
you can reschedule the activity by giving it another early start date, change
the duration of the activity by changing the number of work days, or allocate
more resources.
- Perform new resource calculations, and observe how your changes affect the
graph.
Note: For an example of a resource capacity calculation,
you can refer to the capacity calculation ID P101, which considers Project P101
and the allocated resources as described above. Look at the resource capacity summary
for Resource ID E10. This resource is over allocated during Period 40. By clicking
the red-topped bar, you can see that the resource has been allocated to both Activities
10020 and 10030 for a total of 130 hours for this period 40. However, the resource's
maximum capacity for this period is 100 hours. Possible solutions are increasing
the activity's number of workdays, changing when these two activities occur so that
they do not overlap in time, or increasing the defined capacity for Resource E10.