Set Work Order Status to Prepared

Explanation

This activity is used to change the work order status to Prepared so that the CBS server can schedule resources for it.

Prerequisites

System Effects

Window

Prepare Work Order
Work Order Execution Logic

Related Window Descriptions

Prepare Work Order
Work Order Execution Logic
Schedule Standalone Work Order - Dialog Box
Change Work Order Status and Schedule Work Orders - Dialog Box   

Procedure

  1. Open the Prepare Work Order or Work Order Execution Logic window and query for the relevant work order.
  2. Right-click the window, point to Work Order Status and click Prepare.
  3. In case the work order is not connected to a project or is part of a work order structure, it will be scheduled immediately. If the work order is part of a work order structure or a project the Change Work Order Status and Schedule Work Orders dialog box will appear. Specify if the whole work order structure or the whole project should be considered when scheduling by selecting the appropriate check box.

If the work order is not connected to a project or is not included in a work order structure:

  1. The Schedule Standalone Work Order dialog box opens.
  2. Select the As Late as Possible check box if you want the scheduling server to place the orders as close as possible to their given need date.
  3. Select the Compress Downstream from Bottleneck check box if you want the scheduling server to try to keep the work order operations as close as possible to the bottleneck resource.
  4. Select the Refresh Materials check box if you want the system to update the scheduling server with the current material availability profile for the site. 
  5. Click OK.

If the work order is part of a work order structure or a project:

  1.  The Change Work Order Status and Schedule Work Orders dialog box opens.
  2. Specify if the whole work order structure or the whole project should be considered when scheduling by selecting the appropriate check box.
  3. Click OK.