Withdraw Material to a project

Explanation

When using IFS/Inventory to issue material to a Project Activity with IFS/Project, you have the option to create a Project Transaction automatically. The internal price of the created transaction will be set to the standard cost of the inventory article. If a margin is connected to the project, then this is used to calculate the sales price, otherwise the sales price is set equal to the internal price. 

Note that supplier invoices for inventory parts normally should not be forwarded to the project, since transactions will be created for these when issuing the part

Prerequisites

Material must be available in IFS/Inventory. 

Window

Project Info/Procurement/Miscellaneous

Related Window Descriptions

Project Info/Procurement/Miscellaneous

Procedure

  1. Select a material item, and select the RMB choice 'Issue from Inventory'.
  2. Enter desired 'Issue Quantity' in the corresponding field.
  3. Select Ok.