Add Shop Order Operation
Explanation
This activity is used to add an operation that is not registered in the parent part's
operation list, e.g., an operation that is needed only for this shop order.
Outside operations added to the released shop orders will create the appropriate type of supply, based on the
outside operation supply type.
(Refer About Routing Master Data.)
Prerequisites
- The shop order must have a status of Released or lower.
- Succeeding outside operations must not have been
started for the newly added outside operations.
System Effects
As a result of this activity,
- The system adds an operation to a specific shop order.
This addition affects only this shop order, not the parent part's entire operation list.
- If the shop order is released, a purchase
requisition, a planned purchase order line, or a released purchase order line will be created
for the operation depending on the outside operation supply type.
Window
Shop Order
MRO Shop Order
Disposition
Shop Order - Complex Assembly Repair
Disposition Shop Order
Related Window Descriptions
Shop Order
Shop Order/Operation
Create Outside Operation
MRO Shop Order
MRO Shop Order/Operation
Disposition Shop Order - Complex
Assembly Repair/Operation
Disposition Shop Order - Complex
Assembly Repair
Disposition Shop Order/Operation
Disposition Shop Order
Procedure
- Create a new line in the
Operation tab.
- In the Operation No field, enter a number for the operation.
- In the Operation Description field, enter a description of the operation.
- In the Work Center No field, specify the work center where the operation will be
performed. Use the List of Values to select from available work centers.
- Specify machine time and/or labor time in the Mfg Setup Time, Mfg
Factor, Labor Setup Time, and Labor Factor fields.
- If desired, change the unit of measure for the manufacturing time in the Factor Unit
field.
- If specifying labor setup time, enter values in the Setup Labor Class No and
Crew Size fields. Use the List of Values to select from available values.
- If specifying labor run-time, enter values in the Labor Class No and
Crew Size fields. Use the List of Values to select from available values.
- If the operation is scheduled using CBS, you have
the option to define an overlap time. Enter the value in the CBS Overlap
field.
- Select the appropriate unit from the CBS Overlap
Unit list. The possible values are Percentage and Units.
Note: The meaning of operation overlap is how early a succeeding operation
is allowed to start in relation to its latest scheduled preceding operation
start time. (For further details, refer to the Operation
Overlap about description).
- In the Op Start Date field, enter the start date and time of the operation.
- In the Op Finish Date field, enter the finish date and time of the operation.
- In the Service Type field enter a service type. Use the List of
values to select a suitable value and the component repair order line
connected service type(s) will be listed.
Note: This field is enabled only if the shop order is a repair shop
order and if it is originated from a CRO line.
- Save.