Ship WIP to Supplier

Explanation

Use this activity to update the quantity of items shipped to the supplier.

Note: You can break the outside operation into several shipments to the supplier. You cannot ship more items than are required for the operation or are reported in the operation prior to the outside operation.

Prerequisites

This activity requires that a quantity of parts be reported on the operation prior to the outside operation.

System Effects

Note: The value for the WIP transaction is calculated based on the estimated cost calculation for the shop order and the quantity shipped to the supplier. This means that variations in WIP, either positive or negative, due to differences from standard, such as changes in lot size, material issued, or time reported, will always remain in the shop order internal WIP. These variances will not be transferred to WIP at supplier.

Window

Shop Order
Report Shop Order Operation
Report Work Center Operation

Disposition Shop Order

Related Window Descriptions

Ship Outside Operation Items to Supplier
Shop Order/Operation
Shop Order
Report Shop Order Operations/Subcontract
Report Shop Order Operations
Report Work Center Operations/Subcontract
Report Work Center Operations
Disposition Shop order
Disposition Shop Order/Operations

Procedure

Shop Order, Disposition Shop order:

  1. In the Operation tab, select the outside operation.
  2. Right-click and then click Ship Wip to Supplier.
  3. In the Qty to Ship field, type the quantity you want to send to the supplier.
  4. To ship all remaining quantities, select the Ship Full Qty check box.
  5. Click OK.

Report Shop Order Operation, Report Work Center Operation:

  1. In the Subcontract tab, select the outside operation.
  2. Right-click and then click Ship WIP to Supplier.
  3. In the Qty to Ship field, type the quantity you want to send to the supplier.
  4. To ship all remaining quantities, select the Ship Full Qty check box.
  5. Click OK.