View Overview

Explanation

Use this function to display CRP Workload per Work Center. This window contains a table that displays detailed CRP load information for the shared-site work center depicted in the CRP load graph. The table includes data for all sites to which you have access. 

Prerequisites

Before you can display CRP Workload per Work Center, the following operations must have been completed in CRP Load per Work Center in All Sites:

System Effects

As a result of this activity, CRP Workload per Work Center opens with a display of the CRP workload to be performed in the shared-site work center depicted in the bar graph.

Window

CRP Load per Work Center in All Sites

Related Window Descriptions

CRP Load per Work Center in All Sites
CRP Load per Work Center Department
CRP Load per Production Line
CRP Load per Work Center

Procedure

  1. Populate CRP Load per Work Center in All Sites with data.
  2. In the list box, select a work center number.
  3. Specify a time span in the From Date and To Date fields.
  4. With the cursor in the upper section of the window, click the right mouse button, then select View Overview.
  5. To display an overview of the CRP workloads for another work center or time span, repopulate CRP Load per Work Center in All Sites, specify the new parameters, then click the right mouse button and select View Overview.