Select PMRP Graph Parameters
Explanation
This activity is used to change the default values for the
period range to be used for generating the Material Plan graph.
Prerequisites
An inventory (PMRP)
part must exist. (Not a level 0 or level 1 part).
System Effects
As a result of this activity, the system will use the specified period range to
generate the material plan graph.
Window
PMRP Material Plan Graph
Related Window Descriptions
PMRP Material Plan Graph
Recalculate Period Template
PMRP Graph Parameters
Procedure
-
In the PMRP Material Plan Graph
window
, right-click and then click Show Graph. The
Select
PMRP Graph Parameters
dialog box opens.
-
Change the default values in the Begin No and
End No
fields by entering the period numbers you want. (If you enter 0 (zero) in the
Begin No field, the system will consider all previous supply and demand
dues when
plotting the graph.
-
Click
OK. The system generates a
material plan graph for the specified period range.