Select PMRP Graph Parameters

Explanation

This activity is used to change the default values for the period range to be used for generating the Material Plan graph. 

Prerequisites

An inventory (PMRP) part must exist. (Not a level 0 or level 1 part). 

System Effects

As a result of this activity, the system will use the specified period range to generate the material plan graph.

Window

PMRP Material Plan Graph

Related Window Descriptions

PMRP Material Plan Graph
Recalculate Period Template

PMRP Graph Parameters

Procedure

  1. In the PMRP Material Plan Graph window , right-click and then click Show Graph. The Select PMRP Graph Parameters dialog box opens.
  2. Change the default values in the Begin No and End No fields by entering the period numbers you want. (If you enter 0 (zero) in the Begin No field, the system will consider all previous supply and demand dues when plotting the graph.
  3. Click OK. The system generates a material plan graph for the specified period range.