Handle Supply Request

Explanation

Perform this activity to handle a supply request for a project demand.

A supply request can either be a Purchase Requisition, Purchase Order, Shop Order or a DOP Header. Each supply type is preposted with the Project ID and activity sequence that has been connected to the project demand. This means that cost, hours and progress are fed back to the connected project activity every time an action is executed on the supply request. However, since the supply request belongs to the project and/or delivery project, any quantity or date change that is done directly on the supply request itself will be questioned, i.e. a question appears to  make the user aware that the supply has originated from project.

Prerequisites

System Effects

Window

Project Navigator

Related Window Descriptions

Project Navigator
Purchase Requisition
Purchase Order
Shop Order
DOP Header

Procedure

  1. Select the project demand line from Project Navigator/Demand/Misc. Parts tab and then select the menu option Purchase Requisition (or Purchase Order, Shop Order Detail, DOP Header Detail) in order to go directly to the supply form. If desired, supply information can also be viewed in Project Navigator/Supply tab.
  2. Follow the relevant activities described in the window descriptions as listed above.