Perform Due Calculation for LLP and Interval Maintenance Tasks

Explanation

This activity is used to perform the due calculation for the interval maintenance of a given serial. The calculation will be done for the serial, based on the registered average operational value per month and the defined maintenance plan. In addition, the due calculation will create a maintenance task, and calculate the remaining life and drop-dead date, for the given serial provided the serial part number is defined as a life limited part and it has reached the days of the forewarning period. The due calculation for a serial will only be done for a maintenance plan connected to an active maintenance program. Therefore, a maintenance program that has an Active status must be connected to the serial before the task calculation can take place. For a calendar based maintenance plan, where no average operational values exist for the primary operational based parameter, there will under certain circumstances only be calculated one record for recurring items. 

Apart from manually performing the due calculation for a serial (as described in this activity), scheduled tasks exist to automatically calculate due dates for all interval based maintenance. The Maintenance Task Calculation scheduled task will be used to calculate the due date for maintenance tasks while the Life Limited Part Calculation scheduled task will be used to calculate the life limit of all serials defined as life limited parts. For more information on the scheduled tasks, refer to the activity Adjust and Verify Background Job for Calculations of LLP Tasks and Adjust and Verify Background Job for Due Calculations for Interval Based Maintenance.

Prerequisites

System Effects

Window

Serial Maintenance  
Component Life
Task Summary
Change Work Scope Tasks

Related Window Descriptions

Serial Maintenance 
Serial Maintenance/Interval Maint.
Serial Maintenance/Next Interval Maint. in Structure 
Serial Maintenance/Life Limited Serials
Component Life
Component Life/General
Task Summary
Task Summary/LLPs
Task Summary/Modification
Change Work Scope Tasks
Change Work Scope Tasks/LLPs
Change Work Scope Tasks/Modification  

Procedure

Use the following procedure to run the due calculation for the interval maintenance of a serial.

  1. Open the Serial Maintenance window or the Component Life window.
  2. Query (F3) for the serial for which you will run the task calculation.
  3. Right-click anywhere in the header of the window and then click Task Calculate to open the Task Calculation dialog box.
  4. If you want to perform task calculation for all serials in the serial structure, select the Calculate Entire Structure check box.
  5. To perform the task calculation as a background job, select the Run in Background check box.
  6. Click OK.

If IFS/Complex MRO is used, the following procedure can be used to calculate due dates for all the tasks (i.e., LLP and Modification tasks) which are to be performed during a shop visit:

  1. Open the Task Summary window or the Change Work Scope Tasks window and query (F3) for the overhaul object and/or the MRO work order number you want.
  2. Right-click anywhere in the header, and then click Calculate All Tasks.
  3. The calculated interval maintenance due dates can be viewed in the LLPs and/or Modification tabs found in the Task Summary window and the Change Work Scope Tasks window.