Project Navigator/Connections
Activity/Connections

[About Activity Connections] [To Project Management]

Usage

Use this window to view the information for objects connected to the selected activity. The Base Currency tab holds values in the company base currency, while the Transaction Currency tab has values in the transaction currency of the object. If project currency is selected on the project the Project Currency tab holds transaction currency values recalculated with the project currency rate type. If Multicurrency Budgeting and Forecasting is selected on the project Base Currency B&F Rate tab will have transaction currency values recalculated with the base B&F currency rate type.

Note: Project currency and multi currency budgeting and forecasting for a project can be enabled in the Project Details/Currency tab.

The window consists of four sub tabs. The upper table window shows the summary of the costs, revenues and hours of the particular connected Object. The lower table window shows the details of the summarized cost, revenues and hours of the selected object in the upper table window. Objects which have been connected manually can be removed in this window while system connections are not removable.

Activity Diagrams

Execute Manual Activity Connected Objects
Analyze Project Performance
Define Project Deliverables and Plan Project Revenue

Activities

Connect Existing Object to Activity
Disconnect Manually Connected Objects
Evaluate Project Connected Objects
Connect Document Package to Activity
Connect Task to Activity
Connect or Register Work Order
Connect Change Order to Activity
Connect a Design Object to a Project Activity
Register Project Demand